Water Channel Construction on Jalan Bougenville Reaches 90 Percent

Progress of the water channel construction located on Jalan Bougenville, RT 03/03, Untung Jawa Island Urban Village, South Seribu Islands Sub-district, Seribu Islands has touched 90 percent. The work has been ongoing since January 2024 and is targeted for completion by the end of February 2024.

It aims to minimize inundation when heavy rain occurs

Untung Jawa Island Urban Village Water Resources (SDA) Coordinator, Mahiar said the total length of the channel being built reached 350 meters with a depth of 1.4 meters and a width of one meter.

This channel from Jalan Bougainville would later be built to Taman Sakura Beach to channel water from land to sea.

New Channel Being Built on Jalan Lebak Bulus I

"It aims to minimize inundation when heavy rain occurs," he expressed, Tuesday (2/20).

He explained it was made using six inches of paralon material which was connected to the drainage control tank for easy monitoring and cleaning.

"It involves ten PPSU personnel. Hopefully, it can effectively prevent inundation," he explained.

Untung Jawa Urban Village Head, Sidartawan uttered the proposal to build a more representative channel was submitted to the Seribu Islands SDA Sub-agency.

"We don't want any puddles to disturb the activities and comfort of tourists and residents," he stated.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1933 personFakhrizal Fakhri
  2. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye1025 personDessy Suciati
  3. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye719 personBudhi Firmansyah Surapati
  4. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye638 personDessy Suciati
  5. New LRT Jakarta Route Set for Official Launch on August 26

    access_time22-08-2026 remove_red_eye499 personDessy Suciati